Repair manual

ASSEMBLY
2-2
Unless otherwise specified, the conveyor travel is
factory set for leftĆtoĆright operation when facing
the front of the oven. If a direction change is reĆ
quired, the polarity of the drive motor must be reĆ
versed. To change the polarity of the drive motor,
disconnect the oven from the power source and inĆ
terchange the black and white motor leads at the
D.C. Controller Board located within the control
box. If the polarity of the motor is changed to
rightĆtoĆleft belt travel, the conveyor belt must
be installed from the left side of the oven inĆ
stead of the right side.
NOTE: Reconfigure the air plates whenever the
conveyor belt direction of travel is
changed.
AIR PLATES
1. Inspect the orientation of the air plates. Refer
to FIGURE 3.
Right Air Plate
Left Air Plate
FIGURE 3
CONVEYOR TUNNEL EXTENSIONS
1. Install the conveyor tunnel extensions over the
conveyor on each end of the oven.
CONVEYOR BELT TENSIONERS
Each tensioner installs between the idle end of the
conveyor (the side opposite the drive) and the
oven's body side.
1. The belt tensioner contain a spring to adjust
the length. Compress the spring to shorten the
length of the belt tensioner.
2. Insert the pin on the end of the tensioner into
the hole in the oven's body side.
3. Expand the tensioner to engage the pin loĆ
cated on the conveyor support.
Conveyor
Support
Belt
Tensioner
Oven Body
Front
Shown without conveyor belt for clarity
FIGURE 4
CRUMB PANS
1. Install the crumb pans under each end of the
conveyor.
NOTE: On stacked ovens, either use perfoĆ
rated crumb pans or install the pans on
the lower oven only.
MOUNT REMOTE CONTROL
1. Mount the remote control unit on a wall within
reach of the computer cables.
2. Connect the computer cables from the controlĆ
ler's rear connector to the connector located at
the rear of the oven.