Commissioning the Fire
Use the sheet on Page 3 to record the results of the commissioning procedure.
This will allow the CVO technical team to resolve any installation issues that
arise. Before starting the fire check it complies with the instructions detailed
earlier in this manual. Check the Data Plate to review the required gas type
and pressure. Light the appliance to allow air to be purged from the system.
This may take a long time depending on the pipe work. Once the pilot lights
switch off the appliance ready for commissioning as detailed below.
RECORD RESULTS IN COMISSIONING SHEET ON PAGE 3
1. Is the appliance sealed to the chimney and room?
2. Is the burner ventilation gap under the shelf free from obstruction?
3. Is there a minimum of 100cm2 purpose provided room ventilation?
4. Is the pipe work fitted suitable for the appliance and inline with the gas
consumption of the appliance?
TEST THE GAS PRESSURE
Carefully remove the front shelf and connect a manometer to the test point
within the appliance. See image below.