Owners manual

1. Secure wall panels together at the corners. Use (4) four 10d coated nails per corner. Nail wall
panels to the floor. Nail through the bottom plate. Space 10d sinkers 24" apart.
Important: The sidewall panels marked with the letter 'F' will be at
the front of the floor.
Nail the wall panels to the floor using 10d sinkers.
2. Install the front wall frames, assembled above, to the sidewalls. Set the front gable on lower
wall frames. Secure with 2-1/2" wood screws.
3. Remove the 2x4 boards attached to the shipping pallet. Brace with a 2x4 on the right sidewall
where they join together. Brace with (20 two 2x4s at the front wall to hold the wall straight.
4. Locate the arch door header and remove packing blocks from the ends. Install the header
between the front wall frames. The siding on the bottom projects past the 2x4 frame on one
side.
This side needs to be towards the outside to receive the upper siding.
5. Nail along the siding edge where it overlaps the 10' long panel.
Step 8 Set Wall Panels
F
F
Step 7 Assemble Front Wall
1. Install (2) two 72" wall studs between
26-1/2" 2x4 plates.
2. Install a 23-1/2" long 2x4 as a siding
backer between the wall studs.
3. Repeat to assemble another wall frame.
32"
Siding Backer
10' Long Rear
Wall Panel
Nail Along Siding Edge
2x4 Bracing