Installation & Assembly
3. Install metal flashing on top of the
siding. Nail with a couple of 6d galv.
nails to hold the flashing in place
until the siding is installed next.
4. Install flashing on opposite wall.
Metal Flashing
4. Cut a 2x4-6' board in half and install the 3' long 2x4
over the front wall plate, butt against the gable frame.
Use 10d sinkers.
5. Install a 6' long 2x4 next and cut
the 2nd 3' long 2x4 to fit against
gable frame. Use 10d sinkers.
1. Position a pre-built gable frame on the end wall
flush with outside of 2x4 wall plate. NOT flush
with siding. Secure the frame by toe nailing into
the top plate of the end wall. Use 10d sinkers.
2. Repeat step to install the opposite gable frame.
Step 6 Set Gables - Install 2X4 Tie Plates
Front Wall of Shed