Product Brochure
Table Of Contents
- HD-7P and HD-7W Manual
- Table of Contents
- Introduction
- Shipping Information
- Safety Considerations
- Components
- Specifications
- Frequently Asked Questions
- Installation Checklist
- Installation
- Being Safe
- Tools
- Planning for Electrical Work
- Selecting an Approach Direction
- Selecting a Power Post Location
- Checking Clearances
- Selecting a Location
- Unloading and Unpacking
- Creating Chalk Line Guides
- Moving the Posts into Position
- Installing the Crosstubes
- About Safety Locks
- Installing the Ladders and Top Cap
- Raising the Crosstubes
- Securing the Ladders
- Removing Sheaves
- Installing the Runways
- Installing the First End of the Flex Tube
- Routing the Lifting Cables
- Working with Compression Fittings and Tubing
- Installing the Air Lines
- Installing the Hydraulic Hose
- Installing the Return Line
- Installing the Power Unit
- Filling the Hydraulic Fluid Reservoir
- Installing the Second End of the Flex Tube
- Installing the Pushbutton Air Valve
- Connecting the Return Line
- Connecting the Hydraulic Hose
- Contacting the Electrician
- Connecting to a Power Source
- Installing a Power Disconnect Switch
- Installing a Thermal Disconnect Switch
- About Effective Embedment
- Anchoring the Posts
- Final Leveling
- Installing Accessories
- Lubricating the Lift
- Performing an Operational Test
- Reviewing the Final Checklist
- Operation
- Maintenance
- Troubleshooting
- Wiring Diagrams
- Labels
- Parts Drawings
- Automotive Lift Institute (ALI) Store
- Maintenance Log
HD-7P / HD-7W Four-Post Lifts 21 P/N 5900041 — Rev. M — July 2019
Moving the Posts into Position
Use a Forklift or Shop Crane to move the Posts. You need to have
at least two people
work
together to stand up the Posts.
⚠ DANGER The Posts are heavy and awkward; be very careful when handling them. If they fall
on a person, they will cause injury.
To move the Posts into position:
1. Using a Forklift or Shop Crane, move the four Posts, one at a time, to the inside corners of the
Chalk Line Guides.
Important: Position the Power Post at the location you chose earlier. The other three Posts can go
at any of the remaining Post locations.
2. Stand up each Post.
Have
at least two people
work together to stand up a Post.
⚠ WARNING Be very careful when walking around the Posts; they are not anchored down at this
point, so it is possible to knock them over, which could cause significant injury.
3. Orient each Post as you stand it up.
The inside (where the Lift Head is) of each Post needs to face the inside of the Post across from it
on the other side of the Lift.
4.
Do not anchor the Posts at this point.
You may or may not be anchoring the Posts at all, depending on whether or not you are going to
be using the optional Caster Kit. But even if you are planning on anchoring the Posts eventually,
do not anchor the Posts
now.