10AP Series Two-Post Lifts 24 P/N 5900265Rev. A10 September 2023
To put the Equalizing Cables into position:
Put both Posts either flat on the ground or elevated on a sawhorse or similar. The insides of the
Posts must be accessible, facing up.
Slide the Lift Heads away from the bottom of both Posts. Far enough to provide access to the
bottom of the Lift Post and the Post Sheave.
Reference only do not scale.
Retrieve the two Equalizing Cables for your Lift. Each model has a specific Equalizing Cable length
as noted in the table below.
Model Part Number Equalizing Cable
Assembly Dia. and
Length
10AP 5595752 Ø10 x 10,170 mm
10AP-168 5595753 Ø10 x 11,400 mm
10APX 5595754 Ø10 x 10,790 mm
10APX-181 5595755 Ø10 x 12,005 mm
Remove the Post Sheave from the bottom of both Posts.
Illustration shows the Cable Sheave
near the bottom of the Post.
Reference only do not scale.
NOTICE Keep the Post Sheave, Sheave Pin, and Bolt nearby; you will be re-installing them soon.