Use and Care Manual
Table Of Contents
- Table of Contents
- Introduction
- Shipping Information
- Safety Considerations
- Components
- Specifications
- Installation Checklist
- Installation
- Reviewing the Safety Rules
- Gathering Your Tools
- Preparing for Electrical Work
- Reviewing the Installation Orientation
- Checking Clearances
- Selecting a Location
- Choosing a Wide or Narrow Configuration
- Installing the Safety Assemblies and Positioning the Safety Lock Cable
- Putting the Equalizing Cables into Position
- About Thread Sealants
- Identifying Hydraulic Fittings
- Routing the Hydraulic Hoses
- Creating Chalk Line Guides
- Anchoring the Posts
- Installing the Overhead Assembly and Safety Shutoff Bar
- Installing the Microswitch
- Completing the Equalizing Cables Installation
- Mounting the Power Unit
- Installing the Safety Lock Cable
- Connecting the Hydraulic Hoses
- Installing the Lift Arms
- Double Threaded Rod Installation
- Leveling
- Contact the Electrician
- Electrical Information
- Wiring the Microswitch
- Connecting the Power Unit
- Installing a Power Disconnect Switch
- Installing a Thermal Disconnect Switch
- Lubricating the Lift
- Review Final Checklist Before Operation
- Leave the Manual with the Owner/Operator
- Perform an Operational Test
- Operation
- Maintenance
- Troubleshooting
- Wiring Diagrams
- Labels
- Parts Drawings
- Automotive Lift Institute (ALI) Store
- Maintenance Log
- Maintenance Log
10AP Series Two-Post Lifts 11 P/N 5900265 — Rev. A10 — September 2023
Installation Checklist
Following are the steps needed to install a 10AP Series Two-Post Lift; perform them in this order.
☐ 1. Review the Safety Rules.
☐ 2. Make sure you have the necessary tools.
☐ 3. Plan for Electrical Work.
☐ 4. Review the Installation Orientation.
☐ 5. Review Clearances around the Lift.
☐ 6. Select the Installation Location.
☐ 7. Choose a Wide or Narrow Configuration (do not proceed until you have chosen).
☐ 8. Install the Safety Assemblies and position the Safety Cable.
☐ 9. Put Equalizing Cables into position.
☐ 10. Add Extension Pieces (10AP-168 or 10AP-181 Models only).
☐ 11. Learn about Hydraulic Fluid contamination.
☐ 12. Learn about Liquid Thread Sealant.
☐ 13. Routing the Hydraulic Hoses.
☐ 14. Create Chalk Line Guides for the Posts.
☐ 15. Anchor the Posts.
☐ 16. Prepare and install the Overhead Assembly and Safety Shutoff Bar.
☐ 17. Install the Microswitch.
☐ 18. Install the Equalizing Cables.
☐ 19. Mount the Power Unit (but do not connect it to power yet).
☐ 20. Route and install the Safety Lock Cable.
☐ 21. Connect the Hydraulic Hoses.
☐ 22. Install the Lift Arm Assemblies.
☐ 23. Perform final Leveling.
☐ 24. Contact the Electrician.
☐ 25. Wire the Microswitch (Electrician required).
☐ 26. Connect the Power Unit (Electrician required).
☐ 27. Install the Power Disconnect Switch and Thermal Disconnect Switch (Electrician required).
☐ 28. Lubricate the Lift.
☐ 29. Perform an Operational Test.
☐ 30. Review the Final Checklist.
☐ 31. Leave the Manual at the Lift for the Owner/Operator.