Technical data
Page 33
BOILERMATE
A-CLASS
OV
2.0 INSTALLATION
2.3 COMMISSIONING
10. DO ensure that the bypass valve for the
heating system (if fitted) is set correctly.
11. DON’T use a combined feed and vent on
BoilerMate installations.
12. DON’T use a BoilerMate on a sealed primary
i.e. closed system.
13. DON’T use pipe smaller than 28mm
between the boiler and the BoilerMate when
the boiler rating exceeds 20kW (about 68,000
Btu/h).
14. DON’T use dipped flow and return between
the boiler and the BoilerMate unless the boiler is
fitted with an overheat thermostat. If necessary
check with the suppliers of the boiler.
15.
DON’T operate the ‘switch’ backup facility
until the system is fully fitted, vented and
commissioned.
16. DON’T place any clothing or other
combustible materials against or on top of
this appliance.