AGATWNDTE01C: Installation Instructions
Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
7
.
A10274
Fig. 6 – Location of Foam Strips
UPFLOW INSTALLATION
NOTE: When the furnaces are positioned back-to-back, the external
extension harness cannot be used on the same side of the furnace that the
return air ducts connect to. Locate harness on opposite side of furnace
where return air is used.
5. Remove the 7/8-in. (22 mm) knockout in the mating side of each
furnace blower compartment. Remove one right side knockout
from one furnace and the left side knockout from the other furnace.
The furnace with the right side knockout removed will become the
Main furnace in side-by-side applications. In back-to-back
applications, either furnace can be the Main furnace.
6. For side-by-side applications insert one snap bushing through each
7/8-in. (22 mm) knockout.
7. Position furnaces against each other on common return-air plenum
(See
Fig. 2). For side-by-side installations, adjust and shim each
furnace to align 7/8-in. (22 mm) knockout in blower compartment,
which will be used for wire routing between furnaces.
8. Drill two 1/8-in. (3 mm) holes, approximately 1-in. (25 mm) below
discharge air flange, from inside top of discharge opening and
through both furnaces.(See
Fig. 7)
9. Drive 1 factory-supplied No. 6 x 3/4-in. (19 mm) LG screw through
each hole and tighten until furnaces are secure and foam strips have
sealed gap between furnaces.
10. Bend or remove flanges on supply air outlet of furnace as shown in
furnace installation instructions.
11. Install indoor coil(s) and/or common supply plenum on supply air
outlet of furnace. Seal all duct connections to furnace with code
approved tape or sealant.
12. Connect common return plenum on furnace. Seal all duct
connections to furnace with code approved tape or sealant.
13. Refer to the furnace installation instructions to complete the
remaining furnace installation.
A93539
Fig. 7 – Furnaces Together at Discharge Opening
DOWNFLOW INSTALLATIONS
NOTE: When the furnaces are positioned back-to-back, the external
extension harness cannot be used on the same side of the furnace that the
return air ducts connect to. Locate harness on opposite side of furnace
where return air is used.
1. Remove the 7/8-in. (22 mm) knockout in the mating side of each
furnace blower compartment. Remove one right side knockout
from one furnace and the left side knockout from the other furnace.
The furnace with the right side knockout removed will become the
Main furnace in side-by-side applications. In back-to-back
applications, either furnace can be the Main furnace.
2. Insert one snap bushing through each 7/8-in. (22 mm) knockout.
3. Bend or remove flanges on supply air outlet of furnace as shown in
furnace installation instructions
4. Position furnaces in the downflow position on the entering air-side
of indoor coils and or common supply plenum. If no approved
cased indoor coil is used, install the furnaces on accessory
combustible floor bases. For side-by-side installations, adjust and
shim each furnace to align unused 7/8-in. (22 mm) knockout in
blower compartment, which will be used for wire routing between
furnaces.
5. Drill two 1/8-in. (3 mm) holes, approximately 1-in. (25 mm) below
return air flange, from inside top of return air opening and through
both furnaces. (See Fig. 8)
6. Drive 1 factory-supplied No. 6 x 3/4-in. (19 mm) LG screw through
each hole and tighten until furnaces are secure and foam strips have
sealed gap between furnaces.
7. Connect common return plenum to furnaces. Seal all duct
connections to furnace with code approved tape or sealant.
A02219
Fig. 8 – Attaching Furnaces Together at Return Air Opening
WARNING
!
UNIT DAMAGE AND FIRE HAZARD
Failure to follow this warning could result in unit damage, fire, personal
injury or death.
DO NOT use the back of the furnace for return-air duct connections as
limit cycling will occur.
SCREW DISCHARGE
OPENINGS TOGETHER