User guide
The Input Files
PCN Process User Guide (301945-A)
Creating and Updating BOMs: 5-15
The SAP List File
OLD_BOM
Part_Number
.saplis
The current BOM for the project you are working on appears in your engineering
directories as a text file named
project
.
saplis
, which is automatically used as the
old BOM to which your new changes will be compared.
Note:
This needs to be specified even for the first time you run
bom_upload
.
This is the BOM as downloaded from the SAP database, for example:
------------------------------------------------------------------------------------------------------
REPORT : ZMRDONCD Bill of Materials / Component Detail Report -Show Initload Mat Rev ECO
TIME: 08:21
CLIENT : 100
DATE: 12/15/1997
PAGE: 1
-----------------------------------------------------------------------------------------------------
Material Group: 920 Plant: 0100
Material Group Desc: SUB-ASSY PCB Validity
Date: 12/15/1997
Parent Material No: 118320-A Rev: 05 Unit of Measure: EA Procurement Type: E
Description: PWB ASSY BLADE CSU E1 DTR Usage Type: 2 MM/PP Status: Special Procurement:
Item Component Validity
Level Number Component Revision Component Description Date ECO
Qty Unit of Item MM/PP Proc Spec
Reference Designator Per Measure Cat. Status Type Proc
------------------------------------------------------------------------------------------------------
1 0002 450-031 00 CAP CER 1206 1500PF 5% 50V NPO 12/01/1997
C9 1.00 EA L F
1 0003 451-021 00 CAP CER 1210 .47UF 10% 50V X7R 12/01/1997
C17,C28 2.00 EA L F
You can download this file from SAP manually, to use with
mechbom
(see
Downloading a .saplis File from SAP
on page 5-8), or you can retrieve it from the
/bay
dir
/dra/rel/pcn_data
archive area, where it is renamed to
Project_rev
.saplis
,
e.g.,
118320-A_05.saplis
.