Instruction Manual
Section 7 not needed if Banks
PowerPDA will be installed. Please
proceed to Section 8.
CAUTION: Do not use force
when working on plastic parts.
Permanent damage to the part
might result.
1. The Power Level Selector switch
will be installed on the driver’s side
of the instrument panel (IP) next to
the steering column (see Figure
45). Carefully remove the IP from
the dashboard by slowly pulling
outwards from the dashboard
around the edges of the IP, allowing
the mounting pins to pull free from
their dashboard sockets. Automatic
transmission equipped vehicles will
need to set the parking brake and
move the shift lever down to the
lowest gear to allow clearance for
instrument panel removal.
Section 7
INSTALLATION OF THE POWER LEVEL SELECTOR SWITCH
Figure 45
�
Figure 46 Power level selector switch template
96776 v.11.0 35