Maintenance Chamber Waterproofing 3.7
When all the installation has been completed, it is necessary to close the maintenance
chamber of the equipment and play the role of waterproof at the same time.
1. Clamp the power cord to the wire position and seal the wire diameter 9 ± 1mm.
2. Put the pigtail / network cable on the wire, and seal the wire diameter 7 ± 1mm.
Power on to Check LED Status 3.8
Power on the gNB, and wait a few minutes while the gNB boots up. Per the previous
Table 1-2 in “1.3 Appearance”, check that the LED indicators are lighting as expected.