Hardware Solutions for Gas Utilities Instruction Manual

ORION® Gas Endpoints, Integral Endpoint for Itron®/Actaris® Residential Slope-Face Gas Meters
2. Screw the endpoint and index onto the gas meter with the three (3) 10-24 X ½" screws (15 in lb. maximum).
Figure 16: Screw endpoint and index onto meter
3. Move the odometer or dial TWO-FEET pawls back and forth to verify pawls are connected. See Figure 17.
Figure 17: Verify pawls are connected
Place the Cover Over the Endpoint and Index
1. Verify the front lens gasket is properly set around the guide pins. See Figure 18.
Figure 18: Verify front lens gasket is properly set
2. Place the cover on the gas meter and tighten it with the four (4) remaining screws (15 inch-pounds maximum). Place the
endpoint IR port on the lower right side of the meter. See Figure 19.
Endpoint IR port
Figure 19: Place cover on meter
The endpoint unit is now ready for programming.
Page 12 July 2014