10
5. The fuse capsule will now be locked and secured.
2.2 Preliminary Check
Complete the following steps to verify that the generator is ready for use.
1. Verify AC Input Voltage
Verify and check to make sure proper AC voltages are available to
power the instrument. The AC voltage range must meet the
acceptable specification as explained in section 2.1.
2. Connect Power
Connect AC power cord to the AC receptacle in the rear panel and
press the power switch to the ON position to turn ON the instrument.
The instrument will have a boot screen while loading, after which the
main screen will be displayed.
3. Self Adjust
At power-on, the waveform generator performs a diagnostic self-test
procedure to check itself for errors.