Operating instructions

Installation
FLOWSIC600 · Operating Instructions · 8010125 V 4.0 · © SICK AG 35
Subject to change without notice
3.3 Mechanical installation
Work on the pipelines to prepare for the installation of the gas flow meter is not included in
the scope of delivery.
It is recommended to use the following tools, equipment and supplies for installation of the
FLOWSIC600:
Lifting gear or fork lift (with sufficient capacity to lift meter or meter-piping assembly)
Box wrench with size suitable for flange installation
Thread seal (e.g. PTFE tape) and flange gaskets
Bolt lubricant,
Leak detection spray
3.3.1 Choosing flanges, seals and other parts
Use pipeline flanges, bolts, nuts, and seals that withstand the maximum operational
pressure and temperature, as well as ambient and operational conditions (external and
internal corrosion) for the flange connections. For installation lengths and flange
dimensions, see MDR.
WARNING: DANGER
Always observe the general safety regulations and safety instructions given
in Section 1 when carrying out any installation work.
The FLOWSIC600 must only be mounted on depressurized and vented
pipelines.
Take all necessary precautions to avoid local or plant-specific dangers.
WARNING: DANGER
Always strictly observe the safety instructions for the installation of
pressure equipment including the connection of several pressure
components set forth in the local or national relations and standards or
Pressure Equipment Directive 97/23/EC.
Installation staff must be familiar with the directives and standards
applicable for pipeline construction.