User's Manual

AZALEA MSR4K44S INSTALLATION GUIDE
COPYRIGHT 2007 AZALEA NETWORKS
24
8 Ethernet Cable Installation
Ethernet cable connects MSR4K44S mesh network to wire network. Ethernet cable is
needed, only when MSR4K44S used as gateway. The performance of network cable
will degrade seriously with length longer than 100 meters. So in MSR nodes
planning, it is better to choose access point to wire network within 100 meters.
The process of Ethernet cable installation
1 Unscrew the protective cap on the Ethernet enclosure.
2 plug Ethernet cable RJ45 head to MSR4K44S Ethernet interface.
3 Water proof the connection by wiring insulation Adhesive Tape and PVC
insulation type;
9 Power Cord Installation
MSR4K44S use 110-220V AC as power, the power interface is on the left bottom of
MSR4K44S. Power cable should be the last step of installation.
Tools: Diagonal Plierspaper knife
The procedure of power cable installation:
1 Point the female power plug to MSR4K44S power port
2 lug the power cable firmly to the port, further tighten the connection by turning
the coupling ring, (which is already attached to the plug) clockwise;
3 Water proof the connection by wiring insulation Adhesive Tape and PVC
insulation type;
4 Secure the power cable follow to the pole with strap, but don’t make it too tight
5 The other side of power cable plug use normal 3 male pin connection to power
supply.
Installation of power cable must be done by experienced technician. Please
read the installation manual carefully before installation.
Before finally power up MSR4K44S, make sure grounding is done correctly