Technical data
IV.5.3 Commissioning
Our applications department can help you with commissioning.
Preparation
— switch off the supply voltages
— detach plug X4 from the servo amplifier
— check LB1 (final speed), change solder link if necessary
— set enable signal to 0V
— switch on aux. voltage 25V DC and PC, start operator software BS7200
Setting parameters
— set parameter “ROD resolution” to 1024 incr./turn
— adjust parameter “Final limit speed” to the setting of LB1
— set parameter “I/O” to 1:1 control
— set parameter “Ramp +” to 2ms
— set parameter “Ramp –” to 2ms
— store the parameter set in the EEPROM
— switch of the 25V DC aux. voltage
Optimization
— connect plug X4 to the servo amplifier, switch on the voltages
— optimization : offset adjustment with potentiometer P303
AC gain adjustment with potentiometer P305
continue in the same way as the corresponding description in the BS7200 manual.
IV.5.4 Position of the connectors and control elements - A.4.011.4/27
Page IV - 8 Interfaces and options Chapter IV
01.98 - A.4.011.4/27 digifas™ 7100 series