4.5. Commissioning
Once all connections are made the equipment is ready for commissioning.
To commission the system the test equipment detailed in Section 5.2. will be required.
Using the system diagrams and the end-to-end test specification (supplied with the equipment), the
equipment should be tested to ensure correct operation.
On initial power up the system alarm indicators on the front door of the equipment should be checked.
A red LED illuminated indicates a fault that must be investigated before proceeding with the
commissioning. A green LED indicates that the power supply is connected to the unit.
In the event that any part of the system does not function correctly as expected, check all connections
to ensure that they are to the correct port, that the interconnecting cables are not faulty and that they
are tightened. The majority of commissioning difficulties arise from problems with the interconnecting
cables and connectors.