User's Manual

c. is in the coverage area.
10. With a pencil, label the cell centre on the floor planwith xCn.
The x is the floor, and
n is the cell number in sequenceof the entire plan.
11. Place the deployment tool at each cell centre to locate the cell boundary.
12.
Mark the cell boundary on the floor plan.
13. Repeat this task for the remaining coverage area from the extremes of the coverage
area toward the centre until the entire floor has been covered.
14. If the cell boundary covers any other critical points, ignore these critical points when
proceeding with coverage deployment.
Note:
If it is not possible to place the basestation at the exact crossover points of the
arcs, place the basestation as close as possible to the crossover.
Double cell deployment
Use the double cell technique only if referred here from the single-cell technique. Before
beginning this technique, there must be two critical points that one cell centre cannot serve.
Using the double cell technique, find two locations for cell centres that cover three critical
points, as shown in Figure 61: Double cell distance on page 99.
Figure 61: Double cell distance
Double cell deployment
1.
Mark a third critical point mid-way between the two critical points already
identified.
2. Place the deployment tool at this mid-way critical point.
3. Establish a link.
Single and multiple floor deployment
DMC DECT Fundamentals August 2012 99