Figure 58: Deployment Kit 2 basestation
Deploying DECT
T
o deploy a DECT system follow
Deploying a DECT system on page 91
.
Deploying a DECT system
1. Identify and mark initial critical points.
Mark critical initial points on the floor plan with the symbol:
Figure 31: Example of initial critical points on page 67 shows the initial critical points:
P1, P2, P3, P5, P6 and P7.
2.
Demarcate the cell contour for the critical point farthest from the centre of the full
coverage area.
To demarcate a cell contour:
a. Set up the deployment tool basestation. Raise the deployment tool
basestation as high as possible, or until it is at the height recommended
for basestations.
b. Establish a link. See
Deployment tool on page 76 for details.
c. Measure the range into the coverage area in a few directions to
determine where a cell centre can be located and still be within range of
Deploying DECT