User's Manual
24 Site planning
Figure 4
Example of a site coverage floor plan
Procedure 2
Obtaining site plans
Step Action
1 Obtain two site plans or maps, with dimensions marked.
Use one working copy to identify critical points, cell centers,
and cell boundaries. Use one clean copy to attach to the site
provisioning record for the installer, customer, or maintenance.
--End--
Gather building information
Gather the following information and enter it into the work order.
Procedure 3
Gathering building information
Step Action
1 Obtain and record building identification.
2 Obtain and record information about construction materials, such
as walls, floors, and ceilings.
3 Record the type facilities, such as office, hotel, factory, store.
4 Record the number of floors in the building.
Nortel Communication Server 1000
SIP DECT Fundamentals
NN43120-123 01.07
6 January 2009
Copyright © 2008-2009 Nortel Networks
.