Specifications

33
User’s Manual
9.4.3 Bottom tower section
A. Follow same installation instructions as on points A and B for intermediate tower section.
B. Position the cabin inside the bottom tower section. See figures below:
9.5 Assembly on site
When the bottom section is erected:
A. Install the first ladder section according to the installation drawing and figure below. Adjust using the
levelling screws.
B. Install the bottom platform control box and connect with all the cable connections with the electrical
boxes.
C. Install the top mechanical stops and top plate according to the installation drawing and shown on the
figure below.
B. Install the rest platforms approximately
every 9 m according to the installation drawing as
shown on figure below:
C. Install the electric cable arm support like
shown on the figure below according to the
installation drawing.
!
!
!
IMPORTANT!
Not necessary for all intermediate sections.
IMPORTANT!
It is also possible to install the cabin and
bottom mechanical stop on site.
IMPORTANT!
Service lift can be used during installation.