5.3. Test Procedure
10.3.1 Air Discharge:
This test is done on a non-conductive surface. The round discharge tip of the
discharge electrode shall be approached as fast as possible to touch the EUT. After
each discharge, the discharge electrode shall be removed from the EUT. The
generator is then re-triggered for a new single discharge and repeated 10 times for
each pre-selected test point. This procedure shall be repeated until all the air
discharge completed.
10.3.2 Contact Discharge:
All the procedure shall be same as air discharge. Except that the tip of the
discharge electrode shall touch the EUT before the discharge switch is operated.
10.3.3 Indirect discharge for horizontal coupling plane
At least 10 single discharges (in the most sensitive polarity) shall be applied at the
front edge of each HCP opposite the center point of each unit (if applicable) of the
EUT and 0.1m from the front of the EUT. The long axis of the discharge electrode shall
be in the plane of the HCP and perpendicular to its front edge during the discharge.
10.3.4 Indirect discharge for vertical coupling plane
At least 10 single discharges (in the most sensitive polarity) shall be applied to the
center of one vertical edge of the coupling plane. The coupling plane, of dimensions
0.5m X 0.5m, is placed parallel to, and positioned at a distance of 0.1m from the EUT.
Discharges shall be applied to the coupling plane, with this plane in sufficient different
positions that the four faces of the EUT are completely illuminated.
5.4. Test Data
Please refer to the Attachment B.