TIP The Server Address is the name of a machine on your domain or an
IP address for the server.
5 In the Primavera P6 Database Instance Selection dialog box
double-click the desired Instance ID to select it.
6 In the Primavera P6 Project Selection dialog box double-click the
desired project file to open it.
7 Use the
Field Selector Dialog Box (page 616) to override some of the
predefined data import options.
TimeLiner connects to the selected project file.
To import CSV data
1 If the TimeLiner window is not already open, click Home tab Tools
panel TimeLiner
.
2 In the TimeLiner window click the Data Sources tab.
3 Click the Add button and click CSV File.
4 Use the standard Open dialog box to locate the desired project file in
CSV format, and click Open.
5 In the
Field Selector Dialog Box (page 616), use the CSV Import Settings
area to specify how your data should be imported into TimeLiner.
652 | Chapter 14 Simulate Construction Scheduling