installed and setup from the Project Management CD by taking the following
steps:
1 Insert Project Management CD, enter the Product Key and accept the
License Agreement.
2 Make sure Primavera Applications or Components is selected, and
click Next.
3 Select Other Components, and click Next.
4 Select Software Development Kit, and click Next.
5 Continue through clicking Next until the install starts.
6 Once installation is complete, click OK to start the Database
Configuration wizard.
7 Adjust settings in the Software Development Kit Setup dialog box
where appropriate, and click OK.
8 Click Yes for a log file, followed by Finish to complete.
On connecting to PPM 4 - 6 within TimeLiner, a logon dialog box allows
the source link to be selected (a warning occurs if none are present). The user
name and password are not stored in the Autodesk Navisworks file, and will
be prompted for each time.
Once connected, a dialog box allows the user to select which project to open.
A check box determines if all sub-projects are opened.
By default, TimeLiner brings through Start, End, Planned Start, and
Planned End as Start, Finish, BL Start and BL Finish respectively.
Other Primavera dates can be selected through the generic
Field Selector Dialog
Box
(page 616), including Project Activity Codes, Global Activity Codes,
and User Defined Fields.
The TimeLiner hierarchy supports the WBS structure for Project / Activity
hierarchy.
NOTE Due to the nature of the Primavera Project Manager 4 - 6 products using
the SDK for data access, importing data with TimeLiner can take a longer period
of time than other formats.
Primavera P6 (Web Services)
Accessing the Primavera P6 Web Services capability greatly speeds up the time
taken to synchronize TimeLiner and Primavera schedules.
Link to External Project Files | 649