6 Click OK to add the new TimeLiner rule, or Cancel to return to the
TimeLiner Rules dialog box.
To apply TimeLiner rules
1 Open the TimeLiner window, and click the Rules button on the Tasks
tab.
2 Select the check boxes for all rules you want to apply. The rules will be
applied in order.
NOTE You can also click Import/Export Attachment Rules button
which enables you to import/export rules to/from an XML file. Imported
rules will overwrite any current rules with the same name.
3 If Override Current Selections check box is selected, then when the
rules are applied they will replace any existing attached items. Otherwise,
the rules will attach items to the relevant tasks without attached items.
4 Click Apply Rules.
NOTE To validate tasks in your schedule, click the Tasks tab, right-click in the
Task View, and use the Find shortcut menu. This option can be turned on/off
in the Options Editor (ToolsTimeLinerEnable Find check box).
Validate Project Schedule
You can check the validity of your schedule, by identifying items that have
not been included in any task, are duplicated in multiple tasks or, are in
overlapping tasks. This is especially useful, when you use rules to attach tasks.
An item may remain unattached for a number of reasons. For example, a task
in the project scheduling file is omitted, or the geometry item has not been
included in a selection or search set.
To check a schedule
1 If the TimeLiner window is not already open, click Home tab Tools
panel TimeLiner
.
2 In the TimeLiner window, the Tasks tab, right-click the tasks view,
and click Find. If this option is not available, open the Options Editor,
and click ToolsTimeLinerEnable Find check box.