2 Select Planned in the Display Dates drop-down.
To view a Gantt chart for Planned vs Actual dates
1 Click Home tab Tools panel TimeLiner
, and click the
Tasks tab in the TimeLiner window.
2 Select Planned vs Actual in the Display Dates drop-down.
To change a resolution of a Gantt chart
1 Click the Tasks tab in the TimeLiner window.
2 Optional: Use the Display Dates drop-down to customize the displayed
Gantt chart. By default, Planned dates are used.
3 Drag the Zoom slider to adjust the charts resolution. The utmost left
position selects the smallest available increment in the timeline (for
example, days); the utmost right position selects the largest available
increment in the timeline (for example, years).
Attach Tasks to Geometry
Each task needs to be attached to items in the model before 4D simulation
can work. You can create and attach tasks at the same time, or you can create
all tasks first, and then attach them, either separately, or in rule-defined
batches.
Tasks can be attached to the current selection in the Scene View, or any of
the selection sets, or any of the search sets. You can view the type of
attachments in the Attached column. By default, this column is located after
Task Type, but you can move it, for example, in front of the Start column.
640 | Chapter 14 Simulate Construction Scheduling