NOTE You can quickly change the task type for all selected tasks. To do this, press
SHIFT or CTRL key and select required tasks, right-click the selection, and click Fill
Down on the shortcut menu. The task type specified for the first selected task will
be used for all tasks in the range.
To delete a task
1 If the TimeLiner window is not already open, click Home tab Tools
panel TimeLiner
.
2 In the TimeLiner window, the Task tab, right-click the task you want
to delete, and click Delete Task on the shortcut menu.
NOTE Deleting the root-level task deletes all tasks in the hierarchy. If you
made a mistake, use the Undo
button on the Quick Access toolbar to
restore the deleted item.
Use Gantt Charts
The Gantt Chart view in the Tasks tab provides a visual representation of
your tasks. The horizontal axis represents the time span of the project, broken
down into increments (such as days, weeks, months, and years) and the vertical
axis represents the project tasks. Tasks can run sequentially, in parallel, or
overlapping.
You can drag a task to different dates, or click and drag on either end of the
task to extend or shorten its duration. Any changes are automatically updated
in the Task view. Similarly, modifying a field in the Tasks view modifies the
corresponding field on the Gantt Chart view.
To view a Gantt chart for Actual dates
1 Click Home tab Tools panel TimeLiner
, and click the
Tasks tab in the TimeLiner window.
2 Select Actual in the Display Dates drop-down.
To view a Gantt chart for Planned dates
1 Click Home tab Tools panel TimeLiner
, and click the
Tasks tab in the TimeLiner window.
TimeLiner Tasks | 639