Use the left and right arrow buttons at the top of the calendar to move
backwards and forwards a month, respectively, then click on the day
you require.
3 To change the start or end time, click the time unit you want to modify
(hours, minutes or seconds), and enter the value. You can use the left
and right arrow keys to move between the units in the time field.
To copy and paste date/time values
1 In the TimeLiner window, the Tasks tab, right-click the date field you
want to copy, for example Planned Start.
2 Click Copy Date/Time.
3 Right-click in a different date field, and click Paste Date/Time.
NOTE Currently, you cannot use the keyboard shortcuts CTRL + C and CTRL +
V to copy and paste date/time values.
To set or modify the task type
1 In the TimeLiner window, the Tasks tab, click the task you want to
modify.
2 From the Task Type drop-down list, select the type of task you wish
this task to be. By default, you can choose from:
Construct
Demolish
Temporary
The task type defines how the items attached to the task will be displayed
during simulation. For example, a default construction sequence would
start with all items hidden, as the task starts the attached items will be
displayed in transparent green, then as the task ends the attached items
will be displayed as they are in the normal model display (this may be
with materials applied if previously set up in the Presenter tool). Task
types themselves can be defined and new types created on the
Configure
Tab
(page 611).
638 | Chapter 14 Simulate Construction Scheduling