NOTE PlannedStart and End dates will be automatically created, starting from
the current system date and incrementing by one day for each subsequent end
and start date. The Task Type will be set to Construct.
Edit Tasks
You can edit any of the task parameters directly in TimeLiner. However, the
changes you make to tasks imported from external project files will be
overwritten next time you refresh the corresponding data sources.
To change the task name
1 In the TimeLiner window, the Tasks tab, select the row with the task
you want to modify, and click its name.
2 Type in the new name for the task, and press Enter.
Command entry: F2
To change the task date and time
NOTE By default, time is not shown. To show time for tasks, open the Options
Editor, click ToolsTimeLiner, and select the Show Time check box.
1 In the TimeLiner window, the Tasks tab, click the task you want to
modify.
2 Modify the task's date:
Clicking the drop-down button in the Actual Start and Actual End
field opens the calendar, and lets you set the ActualStart/End dates.
Clicking the drop-down button in the Planned Start and Planned
End field opens the calendar, and lets you set the PlannedStart / End
dates.