Planned Against Actual. Choose this view to simulate the Actual
schedule against the Planned schedule. This will highlight the items
attached to the task over the entire Planned and Actual date range (that
is, between the earliest of Actual and PlannedStart dates and the latest
of Actual and PlannedEnd dates. See diagrams below for graphical
representation). For time periods where the Actual dates are within the
Planned dates (on schedule), the items attached to the task will be
displayed in the Task TypeStart Appearance. For time periods where
the Actual dates are early, or late in comparison to the Planned dates
(there is a variance), then the items attached to the task will be displayed
in the Task TypeEarly or Late Appearance, respectively.