Planned. Choose this view to simulate the Planned schedule only (that
is, only use the Planned Start and Planned End dates).
Planned (Actual Differences). Choose this view to simulate the Actual
schedule against the Planned schedule. This view will only highlight the
items attached to the task over the Planned date range (that is, between
PlannedStart and Planned End. See diagram below for graphical
representation). For time periods where the Actual dates are within the
Planned dates (on schedule), the items attached to the task will be
displayed in the Task TypeStart Appearance. For time periods where
the Actual dates are early, or late in comparison to the Planned dates
(there is a variance), then the items attached to the task will be displayed
in the Task TypeEarly or Late Appearance, respectively.
624 | Chapter 14 Simulate Construction Scheduling