Task Types
The tasks types are shown in a multi-column table. You can move and resize
table columns, if necessary.
NOTE You can double-click on the Name column to rename a task type, or
double-click on any other column to change the task type appearance.
TimeLiner comes with three predefined task types:
Construct - for tasks where the attached items are to be constructed. By
default, during a simulation, the objects are highlighted in green at the
start of the task and are reset to Model Appearance (page 657) at the end of
the task.
Demolish - for tasks where the attached items are to be demolished. By
default, during a simulation, the objects are highlighted in red at the start
of the task and are hidden at the end of the task.
Temporary - for tasks where the attached items are only temporary. By
default, during a simulation, the objects are highlighted in yellow at the
start of the task and are hidden at the end of the task.
Add
Adds a new task type.
Delete
Deletes the selected task type.
612 | Chapter 14 Simulate Construction Scheduling