2012

Table Of Contents
6 Select the Enable Find check box if you want the find option to be
available when you right-click in the Tasks tab.
7 Select the time that you want the working day to finish using the End
of Working Day (24h) option.
8 Select the Report Data-Source Import Warnings check box to
enable the displaying of warning messages if an issue is encountered
when importing data in the TimeLiner window, Data Sources tab.
9 Select the Show Time check box to display the time in the date columns
in the Tasks tab.
NOTE You can select the format of the text file that will be used to import/export
a CSV file into TimeLiner in the TimeLiner CSV Dialog Box.
Tasks Tab
The Tasks tab enables you to create and manage project tasks. It shows all of
the tasks in your schedule, listed in a table format. You can use the scroll bars
at the right and at the bottom of the tab to move through the task records.
The Task View
The tasks are shown in a multi-column table, which provides some flexibility
in how records are displayed. You can:
Move or resize columns
Sort column data in ascending or descending order
Overview of TimeLiner Tool | 605