2011

Table Of Contents
To view a Gantt chart for Planned vs Actual dates
1 Click Home tab Tools panel TimeLiner
, and click the Gantt View tab in the TimeLiner window.
2 Select Planned vs Actual in the Display Dates drop-down.
To change a resolution of a Gantt chart
1 Click the Gantt View tab in the TimeLiner window.
2 Optional: Use the Display Dates drop-down to customize the displayed Gantt chart. By default, the Actual
dates are used.
3 Drag the Zoom slider to adjust the charts resolution. The utmost left position selects the smallest available
increment in the timeline (for example, days); the utmost right position selects the largest available increment
in the timeline (for example, years).
Link to External Project Files
One of TimeLiner most powerful features is its integration with project scheduling software. A list of tasks
including their start and end dates/times can be imported from a project file directly into TimeLiner.
Supported Scheduling Software
Autodesk Navisworks TimeLiner supports a variety of scheduling software.
NOTE Some of these may only function if the relevant scheduling software is installed.
412 | Chapter 15 Simulate Construction Scheduling