2011

Table Of Contents
You can use the Links Tab to import tasks from an external source, such as Microsoft Project
. You can
choose a field from the external schedule to define the types of the imported tasks, or you can set task types
by hand. Linked fields cannot be edited directly in TimeLiner. You can, of course, update the schedule
externally and synchronize the tasks in TimeLiner with those from the external source.
3 Attach objects in the model to tasks.
If you used the shortcut menu on the
Tasks Tab to create an initial set of tasks based on layer, item or
selection set names, then the corresponding layers, items or selection sets will already be attached for you.
If you need to manually Attach Tasks to Geometry, you can use the shortcut menu to attach selections,
searches or selection sets.