Add new user columns to the default column set
TIP It is possible to move between entries in a manually editable task using the keyboard. Simply select a task that has
been set to be manually editable, and use Tab and Shift-Tab keyboard keys to move forwards and backwards between
fields. The keyboard can then be used to edit and set each entry where necessary.
The Task Hierarchy
Autodesk Navisworks TimeLiner supports a hierarchical task structure, as brought through from a link to your
scheduling software, for example Microsoft Project
see Links Tab on page 339 for more information). The
hierarchy can be expanded or contracted by clicking on the plus or minus sign, respectively, to the left of the
task.
The Task Icons
An icon is displayed to the left of each task name. These identify the current status of the task, with relation to
attached items and links to external schedules:
Task with no attached items.
Task with attached items.
Task with link synchronized to external schedule.
Task with link synchronized to external schedule, including Task Type.
Task with link to external schedule that is either broken or old (unsynchronized).
The Status Icons
Each task has its own Status identified by an icon, representing planned against actual relationships. Each icon
shows two bars. The top bar represents the Planned dates, and the bottom bar represents the Actual dates. If the
Actual start and finish dates are the same as the Planned start and finish dates, the bars are displayed in green.
Any variations between Planned and Actual dates are displayed in red. Missing Planned or Actual dates are shown
in grey.
Actual start and end dates equal Planned start and end dates.
Actual end date before Planned start date.
Actual start date after Planned end date.
Actual start date before Planned start date and Actual end date after Planned end date.
Actual start date before Planned start date and Actual end date equals Planned end date.
Actual start date equals Planned start date and Actual end date after Planned end date.
Actual start date equals Planned start date and Actual end date before Planned end date.
Actual start date after Planned start date and Actual end date equals Planned end date.
Actual start date before Planned start date and Actual end date before Planned end date.
Actual start date after Planned start date and Actual end date after Planned end date.
Actual start and end dates only.