2009

Table Of Contents
1. Make changes to the project in the scheduling software, and save it.
2. Load your model into NavisWorks (see Opening Files if you need help).
3. Click TimeLiner on the Tools menu, and click the Links tab in the TimeLiner window.
4. Right-click the link to the modified project file, and click one of the following options:
Rebuild Task Hierarchy from Link. Choose this to re-import all tasks and associated
data from the selected project file, and rebuild the task hierarchy on the Tasks tab.
Synchronize Tasks from Link. Choose this to update all existing tasks in the Tasks tab,
with the latest associated data from the selected project file (e.g. Start and End dates).
Alternatively, right-click anywhere in the link view, and click Rebuild Task Hierarchy from All Links.
This enables you to re-import all tasks and associated data from all linked project files, and rebuild
the task hierarchy on the Tasks tab.
Linking to External Project Files