1. Insert Project Management CD, enter the Product Key and accept the License Agreement.
2. Make sure "Primavera Applications or Components" is selected and click "Next".
3. Select "Other Components" and click "Next".
4. Select "Software Development Kit" and click "Next".
5. Continue through clicking "Next" until the install starts.
6. Once installation is complete, click "OK" to start the Database Configuration Wizard.
7. Adjust settings in the Software Development Kit Setup dialog where appropriate, and click "OK".
8. Click "Yes" for a log file, followed by "Finish" to complete.
On connecting to PPM 4 and 5 within TimeLiner, a logon dialog allows the source link to be selected (a
warning occurs if none are present). The user name and password are not stored in the NavisWorks file,
and will be prompted for each time.
Once connected, a dialog box allows the user to select which project to open. A check box determines if
all sub-projects are opened.
By default, TimeLiner brings through Start, End, Planned Start, and Planned End as "Start", "Finish", "BL
Start" and "BL Finish" respectively.
Other Primavera dates can be selected through the generic TimeLiner 'Field Selector' Dialog, including
'Project Activity Codes', 'Global Activity Codes', and 'User Defined Fields'.
The TimeLiner hierarchy supports the WBS structure for Project / Activity hierarchy.
Note:
Due to the nature of the Primavera Project Manager 4 and 5 products using the SDK for data
access, linking with TimeLiner can take a longer period of time than other formats.
Asta Power Project
This Link requires Asta Power Project to be installed.
Adding and Managing Links
In this section you will learn how to create, delete and edit links.
Adding Links
To add a link:
1. If the TimeLiner window is not already open, select Tools > TimeLiner from the menu bar.
Linking to External Project Files