If you want all tasks to have the same task type, click the Task Type field for the first task, then
press Shift, and click the Task Type field for the last task. The task type you select for the last
field will be used for all tasks in the range.
Deleting Tasks
To delete a task:
1. If the TimeLiner window is not already open, select Tools > TimeLiner from the menu bar.
2. In the TimeLiner window, the Task tab, right-click the task you want to delete, and click Delete Task
on the shortcut menu.
Note:
Deleting the root-level task deletes all tasks in the hierarchy. If you made a mistake, use the
button on the Standard toolbar to restore the deleted item.
Attaching Tasks to Geometry
Each task needs to be attached to items in the model before 4D simulation can work. You can create and
attach tasks at the same time, or you can create all tasks first, and then attach them, either separately, or
in rule-defined batches.
Tasks can be attached to the current selection in the main NavisWorks window, or any of the selection
sets, or any of the search sets. You can view the type of attachments in the Attached column. By default,
this column is located after Task Type, but you can move it, for example, in front of the Start column:
TimeLiner Tasks