Actual against Planned. Choose this view to simulate the Actual schedule against the Planned
schedule. This will highlight the items attached to the task over the entire Planned and Actual date
range (i.e. between the earliest of Actual and Planned start dates and the latest of Actual and Planned
End dates. See diagrams below for graphical representation). For time periods where the Actual dates
are within the Planned dates (on schedule), the items attached to the task will be displayed in the Task
Type Start Appearance. For time periods where the Actual dates are early, or late in comparison to the
Planned dates (there is a variance), then the items attached to the task will be displayed in the Task
Type Early or Late Appearance, respectively.