2009

Table Of Contents
Planned. Choose this view to simulate the Planned schedule only (i.e. only use the Planned start and
Planned end dates).
Planned (Actual Differences). Choose this view to simulate the Actual schedule against the
Planned schedule. This view will only highlight the items attached to the task over the Planned date
range (i.e. between Planned Start and Planned End. See diagram below for graphical representation).
For time periods where the Actual dates are within the Planned dates (on schedule), the items
attached to the task will be displayed in the Task Type Start Appearance. For time periods where the
Actual dates are early, or late in comparison to the Planned dates (there is a variance), then the items
attached to the task will be displayed in the Task Type Early or Late Appearance, respectively.
Overview of TimeLiner
454