Task with link synchronized to external schedule.
Task with link synchronized to external schedule, including Task Type.
Task with link to external schedule that is either broken or old (unsynchronized).
The Status Icons
Each task has its own Status identified by an icon, representing planned against actual relationships.
Each icon shows two bars. The top bar represents the Planned dates, and the bottom bar represents the
Actual dates. If the Actual start and finish dates are the same as the Planned start and finish dates, the
bars are displayed in green. Any variations between Planned and Actual dates are displayed in red.
Missing Planned or Actual dates are shown in grey.
Actual start and end dates equal Planned start and end dates.
Actual end date before Planned start date.
Actual start date after Planned end date.
Actual start date before Planned start date and Actual end date after Planned
end date.
Actual start date before Planned start date and Actual end date equals Planned
end date.
Actual start date equals Planned start date and Actual end date after Planned
end date.
Actual start date equals Planned start date and Actual end date before Planned
end date.
Actual start date after Planned start date and Actual end date equals Planned
end date.
Actual start date before Planned start date and Actual end date before Planned
end date.
Actual start date after Planned start date and Actual end date after Planned end
date.
Actual start and end dates only.
Planned start and end dates only.
Overview of TimeLiner