2011

Table Of Contents
3 Select the Simulation check box in the Display area.
4 If the TimeLiner window is not already open, click Home tab Tools panel TimeLiner
, and click
the Simulation tab.
5 In the Clash Detective window, Results tab, select a clash in the Results list.
6 The simulation slider in the TimeLiner window is moved to the exact point at which the clash occurs. You
can move the slider to investigate the events happening immediately before and after the clash.
7 Repeat this process to review all found clashes.
Report Clash Results
You can produce various Clash Detective reports. For example, you may need a report that will enable planners
to adjust the project schedule in their 3rd party scheduling software.
For time-based clashes, it may be helpful to include in the report additional information about each static package
in the clash. This information can be set up in the Options Editor by using the Quick Properties definitions.
To create a clash report
1 In the Clash Detective window, run the desired test (individually, or as a batch). If you run a batch test, on
the Batch tab, select the test you want to view the results for.
2 Click the Report tab.
454 | Chapter 16 Locate and Manage Interferences