Simulate Construction
Scheduling
The TimeLiner tool enables you to link your 3D model to an external construction
schedule for visual 4D planning.
Overview of TimeLiner Tool
The TimeLiner tool adds 4D schedule simulation to Autodesk
Navisworks Manage 2010. TimeLiner imports schedules from a
variety of sources, allows you to connect objects in the model with
tasks in the schedule and simulate the schedule showing the effects
on the model, including planned against actual schedules. TimeLiner
also allows the export of images and animations based on the results
of the simulation. TimeLiner will automatically update the
simulation if the model or schedule changes.
You can combine the functionality of TimeLiner with other Autodesk
Navisworks tools:
Linking TimeLiner and Object Animation together enables the
triggering and scheduling of object movement based on start
time and duration of project tasks, and can help you with
workspace and process planning. For example, a TimeLiner
sequence may indicate that when a particular site crane moves
from its start point to its end point over the course of a particular
afternoon, a workgroup working nearby causes an obstruction
along its route. This potential obstruction problem can be
resolved before going to site (e.g., the crane can be moved along
a different route, the workgroup moved out of the way, or the
project schedule altered). See
Add Animation on page 366 for
more information.
Linking TimeLiner and Clash Detective together enables the
time-based clash checks on the project. See
Locate and Manage
Interferences
on page 371 for further details on time-based
clashing.
Linking TimeLiner, Object Animation, and Clash Detective
together enables clash testing of fully animated TimeLiner
schedules. So, instead of visually inspecting a TimeLiner sequence
to make sure, for example, that the moving crane didn't collide
with a workgroup, you can run a Clash Detective test.