Check Simulation if you want to be able to interact with the animation or project schedule
simulation for the selected clash. This only applies to time-based, soft, or time-based soft clash
testing results.
9. Check the Highlight check box to override the color of the item in the main navigation window with
the color of the status of the selected clash.
10. Click Select to select a clashing item in the main navigation window.
11. Click on any of the column headings to sort the table using that column's data. This sorting can be
alphabetical, numerical, date-related, or, in the case of the Results->Status column, in workflow
order New>Active>Approved>Resolved. Clicking the column heading repeatedly toggles the
sorting between ascending and descending.