default behaviour is to use the most appropriate available date for each
source. This field may be used to specifically define an Actual End date,
should it be different to that selected by default.
Planned Start The field used to identify a planned start date. This allows planned against
actual comparisons to be made and simulated.
Planned End The field used to identify a planned end date. This allows planned against
actual comparisons to be made and simulated.
User 1 to 10 Ten user fields available to link any custom data fields from the project source.
40.3. Standard Links
JetStream TimeLiner supports a variety of scheduling software. Note that some of these may only
function if the relevant scheduling software is installed.
Supported Scheduling Software
Microsoft Project 2000
Microsoft Project 2002
Microsoft Project MPX
Primavera Project Planner
Primavera Project Management 4 and 5
Asta Power Project
40.3.1. Microsoft Project 2000
This Link requires Microsoft Project 2000 to be installed.
40.3.2. Microsoft Project
This Link requires Microsoft Project 2002 to be installed.