Add Task. Choose this to add a new task to the schedule. "New Task" will be created and by default
assigned the present date which you can change by clicking on the drop down icon to the right of the
Start and End dates, then choosing the date you require from the calendar that is displayed:
Note
The dates under the Start and End columns are Actual start and end dates. For Planned start
and end dates, see assigning planned start and end dates.
Use the left and right arrow buttons at the top of the calendar to move backwards and forwards a
month, respectively, then click on the day you require.
Should you wish to change the start or end time, select the task, then click once on the time to
highlight the hour, minute or second field. Once highlighted, you can then edit its value. Use the left
and right arrow keys to move to the next time unit field. The date can also be edited in this way.
Should you also wish to add Planned start and end dates, simply click on the drop down icon to the
right of the Planned Start and Planned End dates, then choose the date you require from the
calendar.
Note
If you have both Actual and Planned dates entered, but would like to disable one or the other,
then this can be done by unchecking the check box to the left of the date.