Lists the drawings available to update in the current project.
Access:
Select to run any of the project-wide commands.
Selects all of the drawings from the project drawing list.Do All
Selects one or more drawings from the project drawing
list.
Process
Moves all selected drawings back to the project drawing
list.
Reset
Moves one or more drawings back to the project drawing
list.
Un-select
Selects drawings by user-defined sections and subsections.by Section/subsection
Task list
Make the changes to the drawing files that have been accumulated while
drawing files were unavailable for editing.
Access:
Click the Project Manager tool. On the Project Manager, click the Project Task
List tool or right-click the project name and select Task List. On the Update from
dialog box, select Update: Select from list of drawings and click OK.
From the Projects menu, select Project Project Manager. On the Project
Manager, click the Project Task List tool or right-click the project name, and
select Task List. On the Update from dialog box, select Update: Select from list
of drawings and click OK.
The tasks that still need to be performed on the selected drawings are listed
in the upper portion of the dialog box. The login name of the user creating
the task, file name, installation and location codes, component tag, type,
Task list | 91