Input activation voltage-Start voltage
0 100 200 300 400 500 600
Grid
connected
disconnected
Status
Vin [V]
Input activation voltage Vstart is the input voltage when the grid connection starts!.
Vstart can be adjusted independent for each MPP-input (Vstart1 & Vstart2)
After start sequence the inverter stays grid connected till the grid voltge went down under 70% of Vstart
Maximal Flexibility in fitting of PV-Array disposition -> Reduction of undesirable grid connection and disconnections.
90
120
140
Easy adjustable via Display!!
Vstart:
Default:
200V for Single phase inverters
Adjustable: 120V-350V
360V for Three phase inverters
Adjstable: 250V-500V
Disconnection: at 70% VStart